The construction project of that marine terminal will be developed on a plot of about 25,830 M ² located in the municipality of Nueva Esparta State Tubores.
This plot is an average of 0.70 meters above sea level, thus requiring to be filled with approximately 56.140M ³ to meet the benchmark established in the project.
The default extension will be built the entire infrastructure of patios, tanks, access roads, parking areas, electrical systems, paving, fencing, demarcation and finishes, also we develop the infrastructure administrative offices and headquarters for the School of Integral Education for the Personnel of Seamanship.
Regarding the development of the pier will be built on piles of metal, using steel pipes to minimize Naval the effect of aquatic environment and seabed; completed the driving of the piles, tie-beam welding and loading as well as the bearing slab, railings and mooring areas. It has been estimated execution time for the work described in approximately 28 to 33 weeks.